Route 15/La Mesa Road/Nisquali Road Interchange |
Description: Victorville - On Route 15 at La Mesa Road/Nisquali Road between Bear Valley Road and Palmdale Road (Route 18). Construct interchange at La Mesa/Nisquali Road and realign frontage roads.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Victorville |
Zip Code | |
Senate District |
17 |
Assembly District | 36 |
Congressional District | 41 |
Caltrans District |
08 |
County/State Route | San Bernardino 15 |
Postmile Begin/End | 38.3 39.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2226 | |
Peak Period Time Savings (minutes) | 54748 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Khalil Saba | (909)884-8276 | Khalil_Saba@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Khalil Saba | (909)884-8276 | Khalil_Saba@dot.ca.gov | |
Right of Way Phase |
Caltrans | Khalil Saba | (909)884-8276 | Khalil_Saba@dot.ca.gov | |
Construction Phase |
Caltrans | Khalil Saba | (909)884-8276 | Khalil_Saba@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$21,324 | $-5,118 | $16,206 | ||||
Non-bond Funding | |||||||
State/Federal* |
$11,530 | $0 | $11,530 | ||||
Local** |
$55,176 | $0 | $55,176 | ||||
Total**** | $88,030 | $-5,118 | $82,912 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,070 | $0 | $1,070 | $133 | |||
Design(PS&E) |
$2,900 | $0 | $2,900 | $2 | |||
Right of Way |
$25,860 | $0 | $25,860 | $0 | |||
Construction |
$58,200 | $-5,118 | $53,082 | $40,680 | |||
Total* | $88,030 | $-5,118 | $82,912 | $40,814 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
09/01/2003 06/30/2007 |
|
09/01/2003 06/30/2007 |
100 | 09/01/2003 06/30/2007 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2006 09/01/2010 |
|
05/01/2006 09/01/2010 |
100 | 05/01/2006 09/01/2010 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/02/2007 08/13/2010 |
|
07/02/2007 08/13/2010 |
100 | 07/02/2007 08/13/2010 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
11/30/2011 12/01/2013 |
|
11/30/2011 12/01/2013 |
100 | 12/07/2011 03/05/2014 |
0 -3 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2014 12/01/2015 |
|
01/01/2014 12/01/2015 |
0 | 03/06/2014 03/04/2015 |
-2 9 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/01/2011 | 10/01/2011 | 0 | 10/01/2011 | 0 | ||
Implementation Date | 10/01/2011 | 10/01/2011 | 0 | 10/01/2011 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2226 | |
Peak Period Time Savings (minutes) | 54748 |
Bond Funding Cost | |
---|---|
Adopted: |
$21,324,000 |
Current Approved: |
$16,206,000 |
Actual Expenditures: |
$15,477,000 |
Status as of December 31, 2023.