Caltrans Logo

Route 15/La Mesa Road/Nisquali Road Interchange

Description: Victorville - On Route 15 at La Mesa Road/Nisquali Road between Bear Valley Road and Palmdale Road (Route 18). Construct interchange at La Mesa/Nisquali Road and realign frontage roads.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Victorville
Zip Code
 
Senate District
17
Assembly District 36
Congressional District 41
 
Caltrans District
08
 
 
County/State Route San Bernardino 15
Postmile Begin/End 38.3 39.4
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      2226  
Peak Period Time Savings (minutes)      54748  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Khalil Saba (909)884-8276   Khalil_Saba@dot.ca.gov
Design (PS&E) Phase
Caltrans Khalil Saba (909)884-8276   Khalil_Saba@dot.ca.gov
Right of Way Phase
Caltrans Khalil Saba (909)884-8276   Khalil_Saba@dot.ca.gov
Construction Phase
Caltrans Khalil Saba (909)884-8276   Khalil_Saba@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$21,324 $-5,118 $16,206
Non-bond Funding
State/Federal*
$11,530 $0 $11,530
Local**
$55,176 $0 $55,176
 
Total**** $88,030 $-5,118 $82,912

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,070 $0 $1,070 $133
Design(PS&E)
$2,900 $0 $2,900 $2
Right of Way
$25,860 $0 $25,860 $0
Construction
$58,200 $-5,118 $53,082 $40,680
 
Total* $88,030 $-5,118 $82,912 $40,814

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2003 

06/30/2007 
 

 
09/01/2003 

06/30/2007 
100  09/01/2003 

06/30/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2006 

09/01/2010 
 

 
05/01/2006 

09/01/2010 
100  05/01/2006 

09/01/2010 


Begin Right of Way Phase

End Right of Way Phase
07/02/2007 

08/13/2010 
 

 
07/02/2007 

08/13/2010 
100  07/02/2007 

08/13/2010 


Begin Construction Phase

End Construction Phase
11/30/2011 

12/01/2013 
 

 
11/30/2011 

12/01/2013 
100  12/07/2011 

03/05/2014 


-3 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

12/01/2015 
 

 
01/01/2014 

12/01/2015 
03/06/2014 

03/04/2015 
-2 

Corridor System Management Plan
Adoption Date 10/01/2011    10/01/2011  10/01/2011 
Implementation Date 10/01/2011    10/01/2011  10/01/2011 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2226
Peak Period Time Savings (minutes) 54748

Bond Funding Cost
Adopted:
$21,324,000
Current Approved:
$16,206,000
Actual Expenditures:
$15,477,000

 

Status as of December 31, 2023.